HONOLULU – The Department of Environmental Services alerts the public of traffic affected next week as city crews and contractors conduct sewer work between the hours of 8:30 a.m. and 3:30 p.m. (or *8 p.m. and 6 a.m.). Dates and locations provided below:
Feb 3-6 | 618-722 Maluniu Avenue | Kailua | Main Rehabilitation |
Feb 4-6 | 526-605 Kainalu Drive | Kailua | Main Rehabilitation |
Feb 5-6 | 240/252 Kalama Street | Kailua | Main Rehabilitation |
Feb 7 | 617/639 Maluniu Avenue | Kailua | Manhole Rehabilitation |
Feb 7 | 526/558 Kainalu Drive | Kailua | Manhole Rehabilitation |
Feb 7 | 1926 Auiki Street | Kalihi-Palama | Main Rehabilitation |
Feb 7 | 2407 Pacific Heights Road | Nuuanu | Main Rehabilitation |
Hart Street/Waiakamilo Road Replacement Sewer Project
Waiakamilo Rd. between Dillingham Blvd. and Hart St.
(1415 Dillingham Blvd. to 420 Waiakamilo Rd.)
URL: Sewer Projects Construction Map