Traffic Advisory – Sewer Work: July 1-5, 2024
HONOLULU – The Department of Environmental Services alerts the public of traffic affected next week as city crews and contractors conduct sewer work between the hours of 8:30 a.m. and 3:30 p.m. (or *8 p.m. and 6 a.m.). Dates and locations provided below:
July 5 |
222 Aloha Tower Drive |
Downtown |
Main Rehabilitation |
July 1 |
5/17 Fort Weaver Road |
Ewa |
Manhole Rehabilitation |
July 1 |
31/33 Hailipo Street |
Ewa |
Manhole Rehabilitation |
July 2-3 |
105 Oneawa Street |
Kailua |
Main Rehabilitation |
July 1 |
528 Alokahi Street |
Kaneohe |
Lateral Rehabilitation |
July 1 |
544/546 Alokahi Place |
Kaneohe |
Manhole Rehabilitation |
July 2 |
537 Alokahi Place |
Kaneohe |
Lateral Rehabilitation |
July 2 |
528/536 Alokahi Place |
Kaneohe |
Manhole Rehabilitation |
July 3 |
550 Alokahi Place |
Kaneohe |
Lateral Rehabilitation |
July 3 |
501 Apapane Street |
Kaneohe |
Manhole Rehabilitation |
July 3 |
492 Malio Place |
Kaneohe |
Manhole Rehabilitation |
July 5 |
545/546 Alokahi Place |
Kaneohe |
Manhole Rehabilitation |
July 5 |
2419 Coyne Street |
Moiliili |
Lateral Rehabilitation |
July 5 |
1967 Aamaka Place |
Pearl City |
Lateral Rehabilitation |
Major sewer projects for July 1-5, 2024
Hart Street/Waiakamilo Road Replacement Sewer Project
Waiakamilo Rd between Dillingham Blvd and Hart St
(1415 Dillingham Blvd to 420 Waiakamilo Rd)
URL: Sewer Projects Construction Map
─ PAU ─